Grand Rapids Area Road Construction

Road Construction Information
August 25, 2010

  1. Ionia Avenue to Eastbound I-196 – the Ionia Avenue entrance ramp will be closed during the reconstruction of I-196 until mid November.
  2. Westbound I-196 to Ottawa Avenue – the Ottawa Avenue exit ramp will be closed during the reconstruction of I-196 until mid November.
  3. Southbound US-131 to eastbound I-196 ramp – the ramp will be closed until early November.
  4. Northland Drive from 14 Mile Road to Indian Lakes Road – Road will be closed for construction until late October.
  5. Ottawa Avenue between Hastings Street and I-196 – Ottawa Avenue will be closed during the reconstruction of I-196 until mid November.
  6. Westbound M-21 (Main Street) between Jackson Street and Hudson Street – westbound M-21 is closed for bridge replacement until early October.
  7. Madison Avenue from Adams to Highland – road closed for reconstruction (local traffic only) until mid October.
  8. Crahen Avenue at Bradford Street – Intersection will be closed for improvements until early September.
  9. I-196 from US-131 to Fuller - There will be a lane closed in each direction until early November.
  10. I-96 from 48th Avenue to 1 Mile east of 8th Avenue – There will be construction in the median causing left shoulder closing and lane shifts until the end of September.
  11. Diamond Avenue over I-196 – The bridge over I-196 will be removed and reconstructed until mid November.
  12. Giles Avenue from 3 Mile to 4 Mile Road – The road will be closed for repair until further notice.
  13. Pettis Avenue from Fulton Street (M-21) to 300’ north of Honey Creek – There will be intermittent lane closures for road work until late September.
  14. 84th Street from 450’ west of Alles Drive to the Grand Elk Railroad – There will be lane closures for road work until early September.
  15. Cascade Road at Hall Street, at Spalding Avenue and Forest Hill Avenue – These intersections will have lane closures for construction until late September.
  16. Alaska Avenue from 68th Street to 84th Street – Road will be closed for reconstruction until mid September.
  17. Fuller Avenue from Knapp Street to Plainfield Avenue – Road will be closed to through traffic for construction until early September.
  18. Walma Avenue from Breton Avenue to 44th Street – Road will be closed to thru traffic until the end of October.
  19. 3 Mile Road between Egypt Valley and Pettis – Road will be closed for road construction until early September.
  20. 32nd Street over US-131 – Lane closures on the bridge with one lane maintained in each direction until early October.
  21. 3 Mile Road over Indian Mill Creek – Road will be close for a bridge replacement from September 1 until late November.
  22. Eastbound I-196 Ramp to College Avenue – The ramp will be closed until early November.
  23. 22 Mile Road over US-131 – Lane closures on the bridge with one lane maintained in each direction until early October.

Road Construction Links

The following links provide additional road construction information. The Grand Valley Metropolitan Council cannot vouch for the content at these external links, however.


The Grand Valley Metropolitan Council would like to
thank for their cooperation on this project.