CURRENTLY PLANNED ROAD IMPROVEMENTS |
![]() |
![]() |
![]() |
![]() |
Year 2000 – 2020 planned and
programmed road improvement projects include (Table 4.2.3 and map above):
|
Table
4.2.3 Georgetown
- Year 2000 – 2020 Planned and Programmed Road Improvements |
|
|
Year |
Improvement |
|
2001-2005 |
Construction of the
South Beltline (M-6)/I-196 interchange |
|
2000
- 2005 |
Reconstruct Cottonwood
Drive (north of Bauer Road) and Fillmore Street |
|
2000
- 2005 |
Widen Port Sheldon
Road (Chicago Drive to 44th Street) |
|
2000
- 2005 |
Widen 44th
Street (Port Sheldon to Kenowa) |
|
2000 |
Widen Baldwin Street
(28th Avenue to Cottonwood Drive) |
|
2001 |
Construct a connector
linking 18th Avenue to 20 Avenue north of Rosewood Street |
|
2000
- 2005 |
Widen Main Street
(Cottonwood Drive to Chicago Drive) |
|
2000
- 2005 |
Widen 28th
Avenue (Port Sheldon to Baldwin Street) |
|
2000
- 2005 |
Widen Baldwin Street
(48th Avenue east approximately a ½ mile) |
|
2006
- 2020 |
Widen Frontage Road
(Port Sheldon to Kenowa) |
|
2006
- 2020 |
Widen Kenowa (44th
Street to Frontage Road) |
|
2006
- 2020 |
Resurface 8th
Avenue (44th Street to Quincy Street) |
|
2000
- 2005 |
Resurface 48th
Avenue (New Holland Street to south of Van Buren Street) |
|
2000
- 2005 |
Resurface 48th
Avenue (Port Sheldon to Bauer Road) |
|
2000
- 2005 |
Resurface Van Buren
Street (48th Avenue to 40th Avenue) |
|
2000
- 2005 |
Resurface 20th
Avenue (Rosewood Street to Baldwin Street) |
|
2000
- 2005 |
Resurface 14th/12th
Avenues (Port Sheldon to Baldwin Street) |
|
2000
- 2005 |
Resurface Port Sheldon
Road (14th Avenue to Chicago Drive) |
|
2000
- 2005 |
Resurface Cottonwood
Drive (Baldwin Street to Bauer Road) |
|
2000
- 2005 |
Baldwin Improvement
Study |
|
NA |
Intersection
modification at 48th Avenue/Port Sheldon Road |
|
NA |
Intersection
modification at Chicago Drive/Main Street |