CURRENTLY PLANNED ROAD IMPROVEMENTS

Year 2000 – 2020 planned and programmed road improvement projects include (Table 4.2.6 and map above):

Table 4.2.6

Year 2000 – 2020 Planned and Programmed Road Improvements

Year

Improvement

2000 - 2005

Widening of Quincy Street (40th Avenue to 32th Avenue)

2000 - 2005

Widening of 32nd Avenue (Quincy Street to north Township boundary)

2006 - 2025

Resurface 8th Avenue (44th Street to Quincy Street)

2006 - 2025

Resurface Byron Road (48th Avenue to 40th Avenue)

2006 - 2025

Resurface 32nd Avenue (Byron Road to Quincy Street)

2006 - 2025

Resurface Riley Street (32nd Avenue to 24th Avenue)

2006 - 2025

Resurface 24th Avenue (Riley Street to Quincy Street)

2006 - 2025

Resurface Quincy Street (24th Avenue to 22nd Avenue)

2006 - 2025

Resurface 22nd Avenue (Quincy Street to New Holland Street)