TIP Amendment to City of Grand Rapids College Avenue Project

The City of Grand Rapids has requested to increase the local share of funding on their FY2022 College Avenue reconstruction project from Leonard to Sweet, which will increase its total budget by more than 25% of the original federally approved budget. The federal funding will not change, and no other projects in the Transportation Improvement Program will be impacted. See below for details.

Original Budget

  • Federal Funding - $725,926

  • Local Participating Funding - $242,824

  • Total Participating Budget - $968,750

  • Non-participating Budget - $1,750,000

Final Budget

  • Federal Funding - $725,926

  • Local Participating Funding - $1,318,264

  • Total Participating Budget - $2,044,190

  • Non-participating Budget - $1,391,069

If you have any questions or comments, please email Laurel Joseph at laurel.joseph@gvmc.org