The City of Hudsonville has requested to increase the total project cost and to remove local non-participating funds to be more in line with updated cost estimates for Highland Drive from 32nd Avenue to Creek View Drive in FY2025. The participating project cost change and modification to a reconstruction project are requiring a federal amendment to the Transportation Improvement Program (TIP). The federal funding will not be changing from the original allocated funds. See below for details.
Programmed Budget
• Federal Funding - $540,729
• Local Funding - $269,271
• Total Budget - $810,000
Proposed Budget
• Federal Funding - $540,729
• Local Funding - $388,706
• Total Budget - $929,435
If you have any questions or comments, please email Michael Zonyk at zonykm@gvmc.org